III.    Planning Process

 

The planning process utilized in Jefferson County was based on the Section 322 local planning requirements of the Disaster Mitigation Act of 2000 and supporting guidance documents developed by FEMA and the West Virginia Office of Emergency Services (WVOES).  The planning process included the following steps, which will be described in greater detail throughout the plan:

 

¨      Step 1: Establish a Core Planning Team

¨      Step 2: Conduct the Risk Assessment

¨      Step 3: Develop Capabilities Assessment

¨      Step 4: Create Mitigation Plan

¨      Step 5: Adopt and Implement Plan

 

This process was led by the Jefferson County Project Impact members and supported by the planning and engineering firm of Edwards & Kelcey (EK). 

 

A.    Jefferson County Project Impact

 

The local hazard mitigation planning process in Jefferson County began when the area was designated as a Project Impact Community.  FEMA Region III and the West Virginia Office of Emergency Services recommended Jefferson County as the fourth and final Project Impact Community in West Virginia based on community commitment and interest.  On May 15, 2001 the Jefferson County Commission entered into a contract with FEMA to provide $300,000 to the community for this initiative.  The county was also required to provide an in-kind match of $100,000, which was accomplished in early 2002. 

 

The Jefferson County Project Impact structure is made up of a steering committee, public awareness/public education committee, partnership development committee, and risk assessment/mitigation planning committee.  The activities undertaken by Jefferson County Project Impact are all overseen by the steering committee, which is made up of county, state, federal, and private entity representatives as described in the table below. 

 

Table 1.  Jefferson County Project Impact Steering Committee Membership

Name

Organization

Darrell Penwell

Jefferson County OES

Barbara Miller

Jefferson County Project Impact Staff

Paul Raco

Jefferson County Department of Planning, Zoning, and Engineering

Jeff Polczynski

Jefferson County Emergency Communications

Katherine Dunbar

Jefferson County Chapter – American Red Cross

John Sherwood

Jefferson Memorial Hospital

Al Hooper

Jefferson County Commission

Richard Crea

Bank of Charles Town

Jane Peters

Jefferson County Development Authority

Chuck Ellison

Frontier Communications

 

 

B.    Risk Assessment and Mitigation Planning Committee

 

One of the early acts of the Jefferson County Project Impact was to establish a Risk Assessment and Mitigation Planning Committee to examine the community’s risks and vulnerabilities to natural and man-made hazards.  This committee, formed in April 2002, comprises representatives from federal, county, municipal, and private entities. 

 

Table 2.  Risk Assessment and Mitigation Planning Committee Membership

Name

Organization

Name

Organization

Paul Raco, Chairman

Jefferson County Department of Planning, Zoning, and Engineering (DPZE)

Steve Bockmiller, Asst. Chairman

Jefferson County Department of Planning, Zoning, and Engineering (DPZE)

Jay Mason

Allegheny Power

Chuck Ellison

Frontier Communications

Frank Welch

Shepherdstown

Joe Walter

Jefferson County Board of Education

Tim Collins, Mayor

Bolivar

Ed Smith

Jefferson County Ambulance Authority

James Addy, Mayor

Harpers Ferry

Dr. Patrick Drohan

Shepherd College – Department of Environmental Studies

James Spradley

Ranson

Nancy Hatcher

Harpers Ferry National Historic Park

Scott Coyle

Charles Town

Steve Deskins

Charles Town Races & Slots

Karin Christensen

US Fish & Wildlife Center – NCTC

Jeff Polczynski

Jefferson County Emergency Communications

Darrell Penwell

Jefferson County OES

Al Hooper

Jefferson County Commission

Jeff Levesque

Jefferson County Chapter – American Red Cross

Ken Greene

Region IX Eastern Panhandle Development Council

Sarah Johnson

Jefferson Memorial Hospital

Grover Boyer

Shepherd College

 

Due to recent federal regulations requiring local hazard mitigation plans, Jefferson County decided to allocate the bulk of its funding and resources to hazard identification, risk assessment, and hazard mitigation planning activities. The Risk Assessment and Mitigation Planning Committee was tasked with most of the activities related to the development of this plan and was considered the Core Planning Team.  Committee members have worked throughout the process from the initial crafting of the Request For Proposal to the final selection and development of the plan (see table below).

 

Table 3.  Jefferson County All Hazard Mitigation Planning Process Timeline

Date

Activity

Purpose

February, 2002

Partnerships formed with community

Establish Project Impact partnership

April, 2002

Risk Assessment/Mitigation Planning Committee formed

Begin risk assessment and mitigation planning process

April, 2002

Contacted other PI Communities

For examples of hazard mitigation plans

April, 2002

Mitigation 101 Educational Workshop

Conducted for Risk Assessment/Mitigation Planning Committee

May 28, 2002

Risk Assessment/Mitigation Planning Committee finalize scope of services and RFP

Make recommendation to Steering Committee

April-June, 2002

Risk Assessment/Mitigation Planning Committee meetings

Data collection

June 15, 2002

Gather existing information from agencies

Data collection

June 19, 2002

FEMA workshop

Training on new planning regulations

June 25-28, 2002

Revised RFP

Update to include DMA 2000 requirements

June 28, 2002

Revised RFP to Scope of Services Committee

Review and approval

July 9, 2002

Scope of Services Committee meeting

Risk Assessment Committee meeting

Finalize RFP for release

July 23, 2002

Steering Committee action

Approved RFP

July 29, 2002

Legal ad for Spirit of Jefferson

Mail out legal ad to list of potential bidders

Advertise RFP

July 30, 2002

WVOES Hazard Mitigation Planning Workshop

Obtain additional information about mitigation planning and state support services

August 1 & 8, 2002

Legal ad to appear in local newspaper

Advertise RFP

August 8, 2002

Prepare Pre-bid packets and presentation

For pre-bid meeting

August 13, 2002

Pre-bid meeting

Mandatory meeting for interested bidders

August 14-29, 2002

PI Office appointments and Q&A period

Review GIS data and obtain clarification on RFP

August 30, 2002

Deadline to submit proposals

Deadline for municipalities to name representatives

Solicit consultant support

For participation on Risk Assessment/Mitigation Planning Committee to meet multi-jurisdictional plan requirements

September 3, 2002

Scope of Services Committee meeting

To open bids and distribute copies

September 3-9, 2002

Scope of Services Committee action

Review of bid documents

September 9, 2002

Scope of Services Committee meeting

Notices to short-listed bidders

To select firms for interview

September 17, 2002

Consultant Interviews

To select firm

September 24, 2002

Steering Committee meeting

Recommendation of selected firm

September 26, 2002

County Commission meeting

Approval of selected firm

October 1, 2002

Notification of selected firm

To commence consultant activities

October 10 & 17, 2002

Legal Notice in The Spirit of Jefferson

Notification of kick-off meeting

October 22, 2002

Kick off meetings

For public officials and general public

October 24, 2002

Quarterly Project Impact Partnership meeting

Signing of contract

 

Hazard identification activity

 

To commence consultant activities

November 4, 2002

Risk Assessment/Mitigation Planning Committee (Core Planning Team) meeting

Focus on risk assessment – data collection, hazard identification

November 28, 2002

Legal Notice in The Spirit of Jefferson

Notification of public meeting

December 2, 2002

Draft risk assessment and maps submitted

For review by core planning team and steering committee

December 5, 2002

Legal Notice in The Spirit of Jefferson

Notification of public meeting

December 9, 2002

Risk Assessment/Mitigation Planning Committee (Core Planning Team) meeting

To present draft risk assessment and obtain comments

December 16, 2002

Public Meeting

To present draft risk assessment and obtain comments

December 17, 2002

Risk Assessment/Mitigation Planning Committee (Core Planning Team) meeting

Develop goals and objectives for mitigation plan

January 10, 2003

Risk Assessment/Mitigation Planning Committee (Core Planning Team) meeting

Develop mitigation strategies

January 29, 2003

Draft Plan submitted

For review by core planning team and steering committee

January 30, 2003

Legal Notice in The Spirit of Jefferson

Notification of public meeting

February 5, 2003

Risk Assessment/Mitigation Planning Committee (Core Planning Team) meeting

To present draft plan and obtain comments

February 6, 2003

Legal Notice in The Spirit of Jefferson

Notification of public meeting

February 10, 2003

Public Meeting

To present draft plan and obtain comments

February 10-March 10, 2003

Public comment period

To obtain public comments

March 7, 2003

Steering Committee meeting

Final plan review

March 10, 2003

Plan to WVOES for review

To obtain state comments

March 13, 2003

Final plan submitted to Jefferson County

Final version with revisions incorporated

March 13, 2003

Jefferson County Commission meeting

Presentation of plan for adoption

March 17, 2003

Charles Town City Council meeting

Presentation of plan for adoption

March 18, 2003

Ranson City Council meeting

Presentation of plan for adoption

April 1, 2003

Bolivar City Council meeting

Presentation of plan for adoption

April 8, 2003

Shepherdstown City Council meeting

Presentation of plan for adoption

April 14, 2003

Harpers Ferry City Council meeting

Presentation of plan for adoption

TBD

Adopted plan submitted to FEMA Region III for approval

Plan comment, review, and approval

TBD

Plan revision

As needed based on FEMA review

June 15, 2004

End of grant period

Jefferson County Project Impact

 

 

 

C.               Public Involvement

 

Throughout the process there were several opportunities for public input.  Three public meetings were held at different stages in the process:  the first to announce the kick-off of the project and describe the planning process; the second to present the initial findings of the draft risk assessment; and the third to present the draft plan.  Each of the meetings was advertised through legal notices in the local newspaper, The Spirit of Jefferson. Copies of the risk assessment and draft plan were made available for the public at various viewing locations in the county and the municipalities.  Information about the planning process and copies of planning documents were also made available on the Jefferson County Project Impact website.  Comment forms were available to the public on the website and also at each display location.  All comments that have been received to date from the public have been reviewed and incorporated into the final version of the plan as appropriate.